Verify the route and lifting plan before production
Final shipping dimensions, weight, road width, turns, slopes, bridge and tunnel limits, overhead clearance, unloading position and crane access must be checked against the selected product.
Prepare the foundation and interfaces
The foundation type, levels, fixing points and utility entries must follow the final drawings, local ground conditions, design loads and local engineering requirements.
Complete destination utilities and local works
Typical interfaces include electricity, water, drainage and sewage, plus data, ventilation or heating where required. Permits and inspections need named responsible parties.
Commission and hand over the finished unit
After placement or M Series assembly, the team completes connections, local finishing, equipment checks, water and electrical tests, inspection records and the agreed handover process.
Coordinate factory and destination work
Installation succeeds when the route, product interface, site preparation and responsibility split are confirmed before shipping.
| Before production | Route, climate, foundation, utilities and permits |
|---|---|
| Before dispatch | Final dimensions, weight, lifting or assembly plan and packing |
| At arrival | Unloading, placement or M Series assembly and connections |
| Handover | Testing, inspection, records and agreed commissioning |
Questions to settle before quotation
- Confirm final dimensions, weight and route
- Prepare crane or assembly work plan
- Complete the approved foundation
- Name utility, permit and inspection responsibilities
A useful quotation identifies the selected model or construction system, approved configuration, quantity, destination, route, utilities, local work and document requirements. Any missing input should be recorded as an assumption or an item requiring confirmation.